ID |
Name |
Scope Of Work |
Funded By |
Period |
Cost |
Work Progress |
---|---|---|---|---|---|---|
1 |
Establishment of Telecommunication and ICT Institute at Gazipur (Phase-1) |
To establish a prestigious Academic Institute for studies in the fields of Science, Engineering and Management for Telecommunication and ICT professionals at degree & post graduate levels. |
BTCL |
2 Years |
Local: 1566.64, Foreign: 731.85 Total: 2298.49 |
100% progress |
3 |
Telecom Tower Building at CTS Compound of BTCL at Tejgaon, Dhaka. |
Number of Floor 17 fl (3 UGE+3 Podium +IIF) Total Floor area: 13,31,125 sq. ft. |
BTCL |
2 years |
Local 36800.00 |
100% progress |
4 |
Replacement of old Digital Telephone System of Dhaka city (171 KL) |
1. NGN based Switching & MGW, MGC, Access gateway 2. PSDN, AAA, NMS 3. FTTX 4. XDSL 5. Optical Fiber 450 km. |
BTCL |
01 Sep 2009 to 30 Jun 2013 Extended to 30 June 2014 Extended to 30 Sep 2014 |
24806.00 lac |
100% progress |
5 |
ILDTS Policy-2007 Compliance Project. |
1. Installation of IGW with NGN facility 2. Installation of ICX at Dhaka, Chittagong, Sylhet, Khulna & Bogra 3. Upgrading BTCL’s existing IIG 4. Central Billing System 5. Computerized Accounting System |
BTCL |
01 Apr 2009 to 30 Sep 2013 Extended to 30 Apr 2014 |
10744.00 lac |
100% progress |
6 |
Optical Fibre Cable Network development in 1000 Union Parishad of Durgam (remote) area |
1. Transmission equipment : STM16 & STM1 Mux 2. a) OFC Network from Upzilla to Union :11500 km b) OFC Network Accessories |
ADP |
4 years |
Local: 89880.12 lac, Foreign: 18151.91 lac, Total: 108031.16 lac (GoB Fund, Equity) |
100% progress |
7 |
Installation of NGN (IMS) based Telecommunication Network for Digital Bangladesh (NTN) |
1. Construction of NGN (IMS) Platforms 2. OFC Network-3500 km 3. Data Center 4. Broadband –FTTX 5. ADSL (100,000 subscriber) 6. Video on Demand, IP TV, Video conference. |
ADP |
01 Mar 2014 to 30 Jun 2017 |
Foreign: 158666.98 lac, Local: 54024.00 lac, Total: 212690.98 lac |
100% progress |
8 |
Installation of Wireless Broadband network for Digital Bangladesh (4G, LTE) |
1. Core Network MME 2. eNode-B BTS at all metropolitn cities, District HQ, Upzilla and growth centers 3. NMS & IN 4. CPE about 10,000 set 5. Transmission equipment to connect all BTS with ASN 6. Optical fiber-300 km |
ADP |
01 May 2014 to 30 Jun 2017 |
Foreign: 56740.57 lac, Local: 18191.03 lac, Total: 74931.60 lac |
100% progress |
9 |
Optical Fiber Cable Network development at Upzilla level (290 Upazilla) |
1. Transmission equipment : STM16 & STM1 Mux 2. a) OFC Network from Upzilla to Union (11060 km) b) OFC Network Accessories 3. Balancing equipment (M/W, SDH Link, Sever ports etc.) |
ADP |
01 Jan 2013 to 31 Dec 2015, Extended to 30 Jun 2016 |
Local: 40470.48 lac, Foreign: 9457.66 lac, Total: 49928.14 lac |
100% progress |
10 |
Optical Fibre Cable Network development in 1000 Union Parishad (1006 Union Parishad) Contact: Project Director, OFCNDP in 1000 UP Phone: 9320258 Project Summary (12Nov2014) |
1. Transmission equipment : STM16 & STM1 Mux 2. a) OFC Network from Upzilla to Union (11060 km) b) OFC Network Accessories 3. Balancing equipment (M/W, SDH Link, Sever ports etc.) |
ADP |
01 (Jan 2012-30 Jun 2014 Extended to 30 Jun 2016) |
Local: 49088.29 lac, Revised: 56824.02 lac, Foreign: 22818.15 lac, Revised: 15073.07 lac, Total: 71906.44 lac, Revised: 71807.09 lac (GoB Fund, Equity) |
100% progress |
11 |
Telecommunication Network Development Project (TNDP) Contact: AGM, TNDP Phone: 9102712 |
1. NGN (IMS) based Telecommunication System with IN & Access Gateway 2. International Gateway Exchange (IGW) 3. National Transmission Backbone OFC Network 1400 km, SDH M/W link 4. Access Facilities-FTTX 5. Wireless Access-WLL 6. ADSL & DSLAM 7. 24/7 National Operation Center (NoC) |
ADP |
01 Jul 2009 - 30 Jun 2013 Extended to: 30 June 2015 |
GOB : 11350.72 lac, P.A : 50935.53 lac, Total : 62286.25 lac |
100% progress |
12 |
Installation of Optical Fiber Cable (OFC) Network at all Govt.College/University and Training Institute Project.Telejogajog Bhaban,37/E, Eskaton Garden, Dhaka-1000.Phone : 02-932-0326 |
1) Cable Purchased from BCS Khulna. 2) OSP Part on Full Turn-key Basis Package-01, Lot-1: Total 178 sites of Dhaka & Mymensingh Division. 3) OSP Part on Full Turn-key Basis Package-01, Lot-2: Total 235 Sites of Barishal, Chittagong, & Khulna Division. 4) OSP Part on Full Turn-key Basis Package-01, Lot-3: Total 174 Sites of Rajshahi, Rangpur & Sylhet Division 5) Equipment Part on full Turn-Key Basis” Package-02, Lot-1, Total 178 Sites of Dhaka & Mymensingh Divisions. 6) Equipment Part on full Turn-Key Basis” Package-02, Lot-2, Total 235 Sites of Barishal, Chittagong & Khulna Divisions . 7) Equipment Part on Full Turn-key Basis Package-02, Lot-3: Total 174 Sites of Rajshahi, Rangpur & Sylhet Division. |
Gob(ADP) |
July, 2018 to December, 2019 |
4498.00 lac |
- |
13 |
Modernization of Telecommunication Network for Digital Connectivity, Telejogajog Bhaban, 37/E, Eskarton Garden, Dhaka-1000 Phone: 41030346 |
The Project covers the following areas: 1. 3 IMS core at Dhaka, Chattogram and Khulna for 1,600,000 subscribers. 2. Access Network for 280,000 FTTH subscribers, 5,100 Offices, 431,120 AGW subscribers. 3. IP Network 4. Transmission Backbone Network DWDM/OTN Backbone transmission Network consists of 8 DWDM ring systems with 100 Gbps per wavelength. 33 DWDM sites and 13 OLA sites are included in backbone transmission network. 5. Metro Network DWDM/OTN Metro transmission system consists of 3 Metro DWDM Ring with 100 Gbps per wavelength in Dhaka and 1 Metro DWDM Ring with 100 Gbps per wavelength in CTG. There are 16 DWDM sites. 6. MSTP Network MSTP Network consists of 21 sites MSTP equipment. 7. NMS/EMS There will be one central NMS/EMS for the DWDM and MSTP system with 17 numbers of clients located at different sites. 8. OFC A total length of 1240.5 km OFC is to be constructed. 9. Microwave 13 hops IP Microwave radio links will be set up at access layers. 10. Support and Management System The BOSS solution provided by vender shall support at least 2 Million subscribers. |
ADP (GoB & Government Concessional Loan of China) |
01 July 2017 to 30 June 2020 |
GOB: 75611.61 lac, Project Aid: 181727.94 lac, Total: 257339.56 lac |
- |
14 |
Development of Switching & Transmission Network to Strengthen Digital Connectivity |
ANS Gateway, IGW, IOS, Billing Platform, DWDM Equipment. |
GoB |
Jan, 2019 to Jun, 2020 |
15538.59 lac |
- |